CS Builders LLC
12/05/2025
Sneak Peak of Fordham Addition Interior 👀
Final Inspections on the horizon ! Finished exterior and complete interior photos to follow ⏭️
01/30/2025
Love to see the Foundation Crew wearing some CS apparel. Judging by that sweatshirt it looks like he’s ready for some new apparel.
C&H Forms moving along here at Fordham. Rebar tomorrow, Inspection Monday AM and then Concrete later that afternoon.
01/15/2025
Deck Frame moving along nicely at the Spillers Lane site.
Stairs, Joist Tape and some blocking on the agenda for tomorrow. !
12/31/2024
Day 1 in the books @ the Fordham addition.
Eliminated 3 windows, installed a temporary WRB until post frame and verified 1st/2nd floor frame heights to save time later on.
Some misc things to move including a fireplace, patio and then we’ll be stripping topsoil and getting this one dug. Look forward to seeing some big forward progression here in the next few weeks between excavation and foundation work.