Holyoke DPW

Holyoke DPW

Share

07/06/2026

*Sewer Lining Update*
While all residents within the River Terrace Phase A project area should check all doors for specific dates and times which will affect their property, the following is a tentative sequencing for upcoming work. Please keep an eye out for notices which will be posted on your doors informing you of exact day and time your property will be affected.

Tentative Schedule for Week of July 6th - July 10th:
Monday, July 6th - Sections of Hillview Rd and Meadowview Rd
Tuesday, July 7th - Sections of Hillview Rd
Wednesday, July 8th - Woodbine Lane and sections of Meadowview Rd
Thursday, July 9th - Sections of Meadowview Rd

07/02/2026

Holiday Trash & Recycling Collection Notice

The City of Holyoke Department of Public Works would like to remind the community that there are NO changes to the trash and recycling collection schedule this week, despite the holiday on Saturday.

🗑️ Please place your trash and recycling curbside on your regularly scheduled collection day.

We wish everyone a safe and happy 4th of July holiday!

Aviso sobre la Recolección de Basura y Reciclaje por el Día Feriado

El Departamento de Obras Públicas de la Ciudad de Holyoke informa a la comunidad que NO habrá cambios en el horario de recolección de basura y reciclaje esta semana, aunque el día feriado sea el Sabado.

🗑️ Coloque la basura y el reciclaje en la acera el día que le corresponde normalmente.

¡Les deseamos a todos un feliz y seguro día feriado!

Send a message to learn more

07/02/2026

CONSTRUCTION UPDATE - Upcoming work will require closure of George St to all Thru Traffic the week of July 6th - July 10th. Residents are requested to seek alternate routes.

We thank you in advance for your patience and cooperation.

Please email Victoria Houle, Assistant City Engineer, at [email protected] with any questions.

Insituform's Cured-in-Place-Pipe (CIPP) 06/29/2026

As part of the River Terrace Phase A Sewer Separation Project, sewer lining work will be performed using a trenchless method known as CIPP lining.

This video provides a general explanation of how the CIPP sewer lining process works.

Watch the video here:

Insituform's Cured-in-Place-Pipe (CIPP) CIPP provides a jointless, seamless, pipe-within-a-pipe with little...

06/29/2026

Sewer lining work on Hillview Rd is scheduled to begin Monday, July 6th, as part of the River Terrace Phase A Sewer Separation Project.

Residents in the River Terrace Phase A project area should watch for door notices over the next few weeks with street-specific updates and 24-hour advance notice before work affects their property.

For residents interested in learning more, we will also share a separate video post explaining the CIPP sewer lining process.

06/24/2026

Construction Update - George St & Jefferson St will be closed Thursday, June 25th. Residents are requested to seek alternate routes. We thank you in advance for your patience and cooperation. Please email Victoria Houle, Assistant City Engineer, at [email protected] with any questions

06/22/2026

Construction Update - George St & Jefferson St will be closed Tuesday, June 23rd through Wednesday, June 24th. Residents are requested to seek alternate routes. We thank you in advance for your patience and cooperation. Please email Victoria Houle, Assistant City Engineer, at [email protected] with any questions.

06/19/2026

*Vadnais St Water Main Update* Water main break has been repaired and services should all be restored. Residents should run water to flush the lines and discoloration on initial running is normal. Please contact Holyoke Water Works at (413) 536-0262 if you experience further issues.

Send a message to learn more

06/19/2026

**Water main break on Vadnais St. Services between George St and Northampton St will be off for the duration of the repair. Repairs expected to take a few hours and additional notices to follow.**

Send a message to learn more

06/11/2026

Construction Update - George St & Jefferson St June 12th - 17th

Want your organization to be the top-listed Government Service in Holyoke?
Click here to claim your Sponsored Listing.

Address


63 N Canal Street
Holyoke, MA
01040

Opening Hours

Monday 8:30am - 4:30pm
Tuesday 8:30am - 4:30pm
Wednesday 8:30am - 4:30pm
Thursday 8:30am - 4:30pm
Friday 8:30am - 4:30pm