MWSIP - Mahaweli Water Security Investment Program
The Mahaweli Water Security Investment Program (MWSIP) will assist the Government of Sri Lanka (GOSL) to complete outstanding water conveyance investments under the Mahaweli Development Program (MDP). Completion of MDP is a key priority of the government and will maximize the productivity of Mahaweli River Basin water resources by transferring available water to dry zone areas of North Central pro
17/05/2026
📍 Pre-Bid Site Visit Successfully Conducted – NCPCP 4
On 15 May 2026, the Mahaweli Water Security Investment Program – Stage II organized its first pre-bid site visit for contract package NCPCP 4
Around 10–12 local and international bidders joined the visit, which began with an awareness session at the RPM Office Conference Hall, Bakamuna, followed by field visits to key project locations.
Officials from the PMU, PIU, and PMDSC provided detailed
briefings on site conditions and project scope, enabling bidders to gain a clear understanding of the works and encouraging strong, competitive participation.
28/04/2026
Progress Update on Tunnel-4 Construction of NCPCP
Significant progress has been achieved in the construction of Tunnel-4 (T-4) under the North Central Province Canal Project. This tunnel section, approximately 1,100 meters in length, is being constructed using the New Austrian Tunnelling Method (NATM), a conventional drill-and-blast technique.
Tunnel-4 extends from the northern tunnel portal to the northern tunnel outlet, covering the section between Chainage Km 54+300 and Km 55+400, in close proximity to Namalpura Village within the Madawala GN Division of the Palugaswewa Divisional Secretariat.
This section plays a critical role in connecting with the 26.6 km tunnel stretch excavated using a Tunnel Boring Machine (TBM), which runs from the northern portal to the southern portal of the canal system.
Construction Progress -
The contractor has recently commenced invert concrete works within Tunnel-4. To date:
Invert concrete has been completed up to Section 32, covering a cumulative length of 346.783 meters.
Crown and wall concrete lining works have been completed up to Section 8 (excluding Section 7), reaching a total length of 83.2 meters.
The Employer has instructed the Engineer to closely monitor both progress and quality, ensuring that construction activities meet the required technical and safety standards.
Click here to claim your Sponsored Listing.
Category
Contact the organization
Telephone
Website
Address
T. B. Jayah Mawatha, Colmobo 10
Colombo
Opening Hours
| Monday | 08:00 - 17:00 |
| Tuesday | 08:00 - 17:00 |
| Wednesday | 08:00 - 17:00 |
| Thursday | 08:00 - 17:00 |
| Friday | 08:00 - 17:00 |