CCL has a long history in providing specialised engineered solutions for buildings and civil structures around the world. The company brings together the latest ideas and specialised techniques for the design and execution of new projects and for the maintenance, repair and strengthening of existing structures. Activities include post-tensioning for buildings and civil structures, slab solutions,

28/02/2022

📢 JOB OPPORTUNITY 📢

CCL is looking for experienced site operatives and site supervisors to work with us on our construction sites throughout the .

This is a fantastic to work on some exciting projects nationwide, working with a team of post-tensioning professionals.

CCL is a global company that provides specialized engineered solutions for structures and has been involved in the construction and engineering of some of the world's most prestigious structures.

❗️ ESSENTIAL REQUIREMENTS ❗️

- Post-tensioning (PT) experience
- Legal right to work in the UK

Get in touch if you are interested in joining our team.
Email your CV to [email protected]

01/02/2022

CCL has designed and installed the for Lighthouse, the tallest residential tower in in cooperation with Ramboll and Per Aarsleff A/S. The post-tensioned slabs are each 200 mm thick and span up to 10 m.

The 142-meter-tower, together with two lower-level side buildings, will provide 400 homes at a unique location at the tip of Aarhus Island, providing first-class views of the city, the bay, and the forest.

11/03/2021

CCL used the Maturix | Real-time concrete monitoring system to monitor concrete strength development at Warwick University Faculty of Arts Building, where the company designed and installed post-tensioned slabs and beams.

Because the Maturix system enables real-time monitoring of the concrete, stressing could be carried out as soon as the designated strength was reached on site. This reduced waiting time, site labour and allowed CCL to optimise the construction schedule while ensuring the integrity of the concrete was maintained.

Usual practice is to cast test specimens for each element and subject these to compression tests in an external laboratory then wait for test results to confirm the correct concrete strength has been reached before stressing can begin.

24/02/2021

After construction of the 41-storey Medore building in began in 2010, it was halted at level seven. CCL was called in last year because the client wished to make major architectural changes and complete floors 8 to 39 using post-tensioning.

After determining the need for repair and strengthening of the existing columns and slabs, CCL carried out the work using and steel column jacketing, external and . The company then installed post-tensioned slabs on floors 8 to 39.

https://www.cclint.com/news/reverse-engineering-helps-shape-solution/

06/01/2021

CCL has completed work on the Bridge. The 100-metre-long balanced structure was the first of its kind in . The bridge has slashed commuting times between 35 local villages for the area’s 100,000 inhabitants.

https://www.cclresourcecentre.com/case-studies/ccl-completes-lebanons-first-balanced-cantilever-bridge/?p=2550&ml=true

Want your business to be the top-listed Engineering Company in Leeds?
Click here to claim your Sponsored Listing.

Telephone

Address


Unit 8 Millennium Drive
Leeds
LS115

Opening Hours

Monday 8am - 4:30pm
Tuesday 8am - 4:30pm
Wednesday 8am - 4:30pm
Thursday 8am - 4:30pm
Friday 8am - 1pm