Photos from Mettle's post 07/04/2026

As works on site begin at Park Row, 383 Wickham Street, we take a moment to bless the project and acknowledge the traditional custodians.

The formalities included a traditional greeting by the Ceremony Master, an incense blessing, and remarks from Lu Li. A ceremonial table was also prepared featuring symbolic gestures representing prosperity, good fortune and a successful build ahead.

Following this, a Welcome to Country & Smoking Ceremony recognised the Traditional Custodians of the land and paid respect to Elders past and present.

To conclude the morning, project partners gathered for a symbolic sod-turn photo opportunity, marking the official start of works at Park Row.

We look forward to seeing this exciting project take shape in the months ahead.

Photos from Mettle's post 27/02/2026

Another milestone delivered at our Ormiston Rise – Building 2 Project

The Team successfully completed a major concrete pour of the Level 2 transfer slab, placing an impressive 330m³ of concrete in a single pour.

The numbers behind the pour:
- 48 concrete trucks ( )
- 2 concrete boom pumps - including one dual-feed setup ()
- Over 20 concreters on site (LJ Crete Group)
- 11 hours to complete

The pour went off without a hitch - this doesn’t happen without planning and teamwork.

A big thank you to all our team, subcontractors & supply partners involved who made this milestone possible.

Another solid step forward in delivery for the Ormiston Rise Community.

Want your business to be the top-listed Engineering Company in Newstead?
Click here to claim your Sponsored Listing.

Address


Level 1, 112 Alfred Street
Newstead, QLD
4006

Opening Hours

Monday 8am - 5pm
Tuesday 8am - 5pm
Wednesday 8am - 5pm
Thursday 8am - 5pm
Friday 8am - 5pm